Import a project schedule
Bring a project's WBS and schedule activities in from a spreadsheet or a P6 export, see what an import will change before you save it, and group activities into flows.
The Project controls tab holds a project's work breakdown structure (WBS) and the schedule activities under it, with each activity's budgeted quantity, hours and cost and its planned and baseline dates. You don't type the schedule in. You import it from a spreadsheet, such as an Excel export from Primavera P6, and import it again whenever the plan changes.
Project controls is an add-on to the Subcontractor Hub, and your organization needs both. Until they are switched on, projects have no Project controls tab and Settings has no Activity flows. Ask Assignar to switch them on for your organization.
You see the tab if you have View projects. Importing needs Update projects, and setting up flows needs Manage settings.
Import a schedule
- Open the project and select the Project controls tab, next to Progress.
- Select Import schedule.
- Select Choose file and pick an .xlsx, .xls or .csv file. To start from a file with the columns in place, select Download template first.
- Read what the import will change (see Check before you import). Nothing is saved yet.
- Select Import. You see "Schedule imported", and the tab shows the schedule.
If someone else imports a schedule for the project, or a flow or cost code the file names is renamed or removed, while you are reading the check, you see "The schedule, its flows or its cost codes changed since the check. Checked again." Read the new counts, then select Import. Nothing is saved from the old check.
Lay out the file
Each row is one activity. Activity ID, Activity Name and WBS Code are required; the other columns are optional. Columns can be in any order, and their headers are matched ignoring case. The activities are read from the first sheet with an Activity ID header in its first three rows.
| Column | Also read from |
|---|---|
| Activity ID | Task Code, Activity Code |
| Activity Name | Task Name |
| WBS Code | WBS, WBS ID |
| WBS Name | |
| Flow | Activity Flow |
| Cost Code | Cost Account |
| Unit | UoM, Unit of Measure |
| Budgeted Quantity | Budget Quantity, Quantity |
| Budgeted Hours | Budget Hours, Budgeted Labor Units, Target Work Qty |
| Budgeted Cost | Budget Cost, Budgeted Total Cost, Target Cost |
| Planned Start, Planned Finish | Target Start Date, Target End Date |
| Baseline Start, Baseline Finish | Revised Baseline Start and Finish, BL Project Start and Finish, BL1 Start and Finish |
A P6 Excel export works as it is, with its field names on one header row and its labels on the next. A column named only Start or Finish is not read, because in P6 those are the current dates, not the plan.
Activity IDs must be unique in the file. A quantity needs a Unit, such as m or m3.
One schedule holds up to 20,000 activities and 5,000 WBS codes, 20 levels deep, from a file of up to 10 MB.
How the WBS is built
Dotted WBS codes make the tree: SF.CIV.EW sits under SF.CIV, which sits under SF. List only the codes your activities use; the codes above them are added for you.
A WBS takes its name from a sheet named WBS with WBS Code and WBS Name columns, then from the WBS Name column, then from a row with a WBS code and a name but no Activity ID, as a P6 export has. A WBS the file doesn't name keeps the name it already has, and a new one is named after the last part of its code, such as EW.
Dates and amounts
A date can be a spreadsheet date, in either of Excel's date systems (some Mac workbooks count from 1904), or text such as 2027-03-01 or 01-Mar-27. An A or an asterisk after a date, as P6 adds to some, is ignored. Dates with slashes follow your organization's region: a United States account reads 03/01/2027 as 1 March 2027, and every other region reads it as 3 January 2027.
Amounts can carry a currency sign and thousands separators, such as $84,000.
Check before you import
When you choose a file, the dialog counts the activities the import will add (Added), change (Updated), leave as they are (Unchanged) and remove (Removed). When the file matches the schedule exactly, the button reads Nothing to import. Select Choose another file to check a different file.
The dialog can also tell you:
- "Flows not set up: Commissioning". A flow in the file must match one of your activity flows by name, ignoring case, and an import never creates one. Select Add these flows to add them and check the file again; you need Manage settings for it. If you import without them, those activities have no flow.
- "Cost codes not found: …" followed by the codes. A cost code in the file must already be one of your cost codes. Those activities import without one.
- "Budgeted cost was not imported: you cannot see costs." Without See cost figures, the Budgeted Cost column is skipped and the costs already stored stay as they are.
- "None of the file's activity IDs are in this schedule. Importing replaces all 42 activities." Check that you are on the right project and that the IDs haven't been renumbered. Importing this file removes every activity on the project and adds the file's.
Update the schedule
Import the new version of the file the same way. Activities are matched by Activity ID, so an activity is updated rather than added twice, and moves when its WBS Code changes. Importing the same file again changes nothing.
- A column you leave out of the file keeps the values already stored for it. A blank cell clears the activity's value in that column.
- Planned Start and Planned Finish count as one column, so include both or neither. The same goes for Baseline Start and Baseline Finish, and for Unit and Budgeted Quantity.
- An activity that isn't in the file is removed unless progress has been recorded against it. An activity with progress is kept and marked Removed. Select Show removed to see it. A later import that includes its Activity ID restores it.
- Once an activity has progress, its unit stays fixed. Keep the original unit, including its letter case, when you import an updated schedule.
- A WBS code the file no longer uses is removed unless a retained activity still references it.
The tab lists activities in the order of the file.
Read the schedule
The tab shows the WBS as a tree, with each activity under its WBS. The columns are Code, Name, Flow, Unit, Quantity, Hours, Cost, Planned start, Planned finish, Baseline start and Baseline finish. A WBS row shows the total Hours and Cost of every activity below it, and their earliest planned start and latest planned finish.
- Type in Search activity ID or name to find activities.
- Choose a flow in All flows to show only its activities. The filter appears once your organization has flows.
- While you search or filter, each WBS with a match is open and its totals still count all of its activities.
- Select the arrow beside a WBS code to open or fold it. The two arrow buttons at the right of the toolbar open or fold every WBS at once.
Without See cost figures, the Cost column shows ——.
Group activities into flows
Flows group activities by trade or stage, such as Civil, Fire Services, Electrical or Commissioning. You need Manage settings.
- In the sidebar, select Settings, then General. Under Operations, select Activity flows.
- Type a name in New flow and select Add.
Select Rename to change a flow's name, then Save. Activities keep their flow, but a file that still uses the old name lists it under "Flows not set up", and importing that file takes the flow off those activities.
Select Archive to take a flow out of the All flows filter. Activities keep it, and an import still matches it. Select Restore to bring it back.
Each name can be used once, ignoring case and including archived flows. Otherwise you see "A flow with that name already exists."
If the file has problems
Assignar Pay reads the file before it checks it. If anything is wrong, the dialog lists each problem with its row number. Fix them in the file and select Choose another file.
| Message | What to do |
|---|---|
| "There is no WBS Code column." | Add the column, or rename its header to one in Lay out the file. |
| "Activity ID is empty.", "A1000 has no name.", "A1000 has no WBS code." | Fill in the cell. |
| "A1000 appears more than once." | Give each activity its own ID. |
| "SF.CIV has two different names." | Use one WBS Name on every row with that WBS code. |
| "Planned Start: 25/03/2027 is not a date." | Use one of the date forms in Dates and amounts. In a United States account, a date with slashes is read month first. |
| "Planned Finish is before the start." | Correct the start or the finish. |
| "Budgeted Hours: 12h is not a number.", "Budgeted Cost is negative." | Enter a number of 0 or more. |
| "A1000 has a quantity but no unit." | Fill in the Unit. |
| "Activity Name is too long." | Shorten it. Activity IDs take up to 60 characters, names 300, WBS codes 200, units 20, flows 80 and cost codes 100. |
| "The file is over 10 MB.", "The file has more than 20000 activities.", "The file has more than 5000 WBS codes.", "SF.CIV.EW… is more than 20 levels deep.", "The file is too large to import." | The schedule is over one of the limits in Lay out the file, or its names and codes are too long to send in one import. |
| "The file could not be read." | Save it again as .xlsx or .csv and choose it again. |
| "Units cannot change for activities with recorded progress: …" | The message names the affected activity. Restore its existing Unit in the file, including the same letter case, then check it again. A blank Unit cell also counts as a change. |
| "The file could not be imported. Check it against the template." | Select Download template and compare its columns with your file. |