Record daily project progress
Save progress and photos against a schedule activity, then submit the day's entry.
Record how far each schedule activity has progressed on the project's Project controls tab. You need Update projects to record, edit, or submit progress. Project controls is part of the Subcontractor Hub.
Save the day's progress
- Open the project and select Project controls.
- Under Daily progress, choose the Day. It starts on your organization's current day.
- Use Find a schedule activity to search by code or name, choose the activity, then select Record progress. This creates a Draft.
- Enter the actual dates, expected finish, remaining days, and Complete (%). Enter the cumulative quantity completed by that day in Quantity to date.
- Add comments and photos, then select Save draft.
There is one entry for each activity on each day. Select Edit to return to a draft. A draft can stay incomplete while you collect the day's information.
Photos use the same location stamp as other photo uploads. Allow location access to save a stamped copy alongside the original. If your device cannot share its location, you see a warning and the original still uploads. You can add up to 10 photos, each up to 10 MB.
To exceed 100% or the activity's budgeted quantity, fill in Reason for exceeding budget. Without it, saving shows "Enter a reason to exceed 100% or the budgeted quantity."
Submit a saved draft
Once the draft has both Complete (%) and Quantity to date, select Submit beside its entry. Its status becomes Submitted, and View opens its saved details. Submitted entries stay read-only.
Draft and submitted progress stays outside job-costing actuals and reports until approval.
If someone else saves first, the latest entry loads automatically. Review its values before entering your changes again. If the activity was removed from the schedule, the editor closes and the activity list refreshes.
Choose today or an earlier day. You cannot record progress for a future day.